The implementation of MetaTune is organized in three macro phases.

W

Phase-1 (M1-M9 / March to December 2026)

This phase is about the preparation activities for the project and the recruitment phase.

W

Phase-2 (M10-M46)

Doctoral candidates are recruited and the research and training activities start.

W

Phase-3 (M46-M48)

At M46, Doctoral candidates contracts with the beneficiaries will end, and the beneficiaries will prepare all final reports.

Work package list descripcion

WP

Name

Leader

Start month

End month

1 Design DTU 10 40
2 Materials INDRA 10 46
3 Fabrication 3DEUS 10 43
4 Characterization JENA 10 46
5 Training KIT 10 48
6 Dissemination UPV 10 48
7 Management UPV 10 48